04/2016 – today |
EDF Energies Nouvelles (Freelance Arrangement) |
|
Heading EPC(I) negotiations |
|
|
11/2010 – 04/2016 |
wpd offshore solutions GmbH |
|
Head of Contracting |
|
Director offshore wind farm Nordergründe |
|
Contract & overall project management |
|
Client’s Representative for all EPCI contracts Butendiek & Nordergründe offshore wind farms (foundations, internal cabling, substation, turbines), “FIDIC Engineer” for the foundation package |
|
Structuring and performance of EPCI tenders |
|
General project execution planning & engineering advise for wpd’s offshore wind projects (mainly Germany, France and Scandinavia) |
|
Performance of commercial and technical negotiations, contracting for EPCI (partly self-drafted, partly adopted LOGIC & FIDIC basis) contracts and minor packages |
|
|
11/2012 |
MWS Certification – Lloyd’s Diploma in Marine Surveying (Accreditation in Non-Liquid Cargo & Warranty Surveys incl. Offshore Units) |
|
|
04/2009 – 09/2010 |
Swiber Holdings Singapore (Freelance Arrangement) |
|
Fleet’s vessel capability analysis with respect to offshore wind farms |
|
Inspection / surveying of vessels & barges |
|
Bid investigation and elaboration for offshore wind farm marine transportation, heavy lift challenges |
|
Elaboration of access strategies to enter the European offshore wind energy market |
|
Preparation of company and office set-up in Germany |
|
|
01/2009 – 03/2010 |
Kronschnabel & Franke Schwerlast Spedition GmbH |
|
Designated General Manager (employed) |
|
Planning and supervision of heavy lift and marine operations |
|
Mobilisation, operation, demobilisation of on- and offshore units |
|
Inspection / surveying of vessels, cranes and barges in Europe and Asia |
|
Re-structuring and implementation of business processes, contracting philosophies, CI |
|
Business development towards Asian offshore companies |
|
|
07/2000 – 12/2008 |
PROKON Nord Energiesysteme GmbH |
|
Head of Projects for offshore wind farms in Germany and France |
|
Assistance for offshore wind farms in UK |
|
Tendering, control, negotiation of contracts and contracting of major and minor supplies (e.g. substations, onshore and subsea cables, support structures, geotechnical and geophysical surveys, installation vessels & equipment) on partly self-drafted and partly standard contract basis in German and English language |
|
Supervision / heading of contractors during design, manufacturing and installation |
|
Supervision / heading of several offshore vessel mobilisation, demobilisation and on-loading tasks |
|
Negotiation of turn-key contracts as a contractor |
|
Realisation and management of the offshore installation spread alpha ventus 2008 |
|
Head of installation (Offshore Construction Manager) alpha ventus 2008 |
|
Assistance, consultancy for AREVA Multibrid |
|
Client’s Rep AREVA Multibrid for alpha ventus |
|
Various M&A processes / Due Diligences / Road Shows |
|
General assistance of departments with respect to legal issues |
|
Consent planning acc. to the respective technical standards |
|
|
11/2003 – 12/2008 |
OWT Offshore Wind Technologie GmbH |
|
General Manager (employed) |
|
Management of engineering & structural design tasks for offshore wind related primary and secondary steel structures |
|
Planning & management of offshore installations |
|
Planning & management of various other offshore-wind related works and tasks |
|
Planning & management of research & development tasks |
|
Preparation and execution of offers, tenders and contracts |
|
|
01/2000 – 06/2000 |
Student trainee at PROKON Nord Energiesysteme GmbH |
|
|
10/1995 – 07/2000 |
University of Oldenburg |
|
Diploma Degree (1,44) |
|
Member of the institute’s executive board |
|
Leader of the students’ council |
|
|
1993 – 1994 |
German Armed Forces |
|
Participant of a NATO challenge |
|
Honoured with battalion’s medal |
|
|
1993 |
A-level (university entrance) degree |